Where the answer is
Look in the general conditions and the supplementary conditions in the front of the Project Manual. Some contracts say the specification governs. Some say the stricter requirement governs. Some say nothing.
What to do before the bid
- Write down the conflict with the section number and the sheet number.
- Send a question to the architect before the question deadline.
- If no answer comes, state your assumption in your proposal.
Common conflicts
- An item is in the spec and not on any sheet.
- An item is drawn and your section does not mention it.
- The spec and a plan note name different products or materials.
- Two sheets show two different counts.